Back to projects

Town of Coalhurst Storm Water Management Improvements

Coalhurst, Alberta

completeWastewaterSCF
Federal contribution
$3.0M
$3,000,000
Federal share22%

of $13.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
20162018202020222024
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Coalhurst
Construction start
Sep 15, 2016(actual)
Construction end
Dec 20, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Aug 1, 2016
  • Construction end11 months earlyforecast Nov 30, 2024

Also in Coalhurst