Town of Beaverlodge Water Treatment Plant Upgrades

Valleyview, Alberta

completeDrinking WaterSCF
Federal contribution
$1.8M
$1,845,000
Federal share33%

of $5.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
201620172018
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Beaverlodge
Construction start
Aug 1, 2015(actual)
Construction end
Oct 16, 2018(actual)

Against the original forecast

  • Construction start7 months earlyforecast Mar 1, 2016
  • Construction end7 weeks lateforecast Aug 30, 2018

Also in Valleyview

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46267 in the federal list. How to read these figures.