Town of Beaverlodge Water Treatment Plant Upgrades
Federal contribution
$1.8M
$1,845,000
Federal share33%
of $5.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
201620172018
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Beaverlodge
- Construction start
- Aug 1, 2015(actual)
- Construction end
- Oct 16, 2018(actual)
Against the original forecast
- Construction start7 months earlyforecast Mar 1, 2016
- Construction end7 weeks lateforecast Aug 30, 2018
Also in Valleyview
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46267 in the federal list. How to read these figures.