Back to projects

Special Areas Board Regional Potable Water Supply Line Extension to Hamlet of Monitor

Special Areas Board, Alberta

completeDrinking WaterSCF
Federal contribution
$822,333
Federal share33%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
20162017
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Special Areas Board
Construction start
Jun 13, 2016(actual)
Construction end
Aug 17, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2016
  • Construction end6 weeks earlyforecast Oct 1, 2017