Village of Delburne 21 Ave Infrastructure Upgrade
Federal contribution
$623,333
Federal share33%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
20162017201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Delburne
- Construction start
- Jun 1, 2016(actual)
- Construction end
- Dec 23, 2019(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2016
- Construction end15 months lateforecast Oct 1, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46272 in the federal list. How to read these figures.