Town of Blackfalds East Area Stormwater Management Plan - Linear Wetland Trunk and Outlet Project.
Federal contribution
$2.4M
$2,398,735
Federal share33%
of $7.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
2016201820202022
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Blackfalds
- Construction start
- Sep 10, 2015(actual)
- Construction end
- Oct 28, 2022(actual)
Against the original forecast
- Construction start20 months earlyforecast May 1, 2017
- Construction end8 weeks lateforecast Sep 1, 2022
Also in Blackfalds
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46273 in the federal list. How to read these figures.