Schedule
Announced and approvedJul 31, 2015
20162017201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Longview
- Construction start
- May 31, 2018(actual)
- Construction end
- Dec 16, 2019(actual)
Against the original forecast
- Construction start4 months earlyforecast Oct 1, 2018
- Construction end4 months earlyforecast Apr 30, 2020