Village of Longview - Water Treatment Plant Upgrades Phase 2

Longview, Alberta

completeDrinking WaterSCF
Federal contribution
$460,000
Federal share26%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
20162017201820192020
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Longview
Construction start
May 31, 2018(actual)
Construction end
Dec 16, 2019(actual)

Against the original forecast

  • Construction start4 months earlyforecast Oct 1, 2018
  • Construction end4 months earlyforecast Apr 30, 2020

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46278 in the federal list. How to read these figures.