Summer Village of Poplar Bay South Side Pigeon Lake-Regional Wastewater System; Local Collection Systems Phase II
Federal contribution
$2.6M
$2,590,129
Federal share33%
of $7.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
201620182020202220242026
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Summer Village of Poplar Bay
- Construction start
- May 31, 2017(actual)
- Construction end
- Dec 31, 2025(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 1, 2017
- Construction end3 months earlyforecast Mar 31, 2026
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46286 in the federal list. How to read these figures.