Town of Pincher Creek Water Treatment Plant UV System Installation and Water Distribution Upgrades
Federal contribution
$600,000
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
2016201720182019
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Pincher Creek
- Construction start
- Nov 1, 2015(actual)
- Construction end
- Aug 31, 2019(actual)
Against the original forecast
- Construction start2 months lateforecast Sep 1, 2015
- Construction end9 months lateforecast Dec 1, 2018