Town of Legal Sanitary Trunk Sewer Upgrade
Federal contribution
$766,667
Federal share33%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
201620172018
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Legal
- Construction start
- Jul 11, 2016(actual)
- Construction end
- Jun 1, 2018(actual)
Against the original forecast
- Construction end9 months lateforecast Aug 30, 2017