County of Thorhild Lagoon Repair, capacity Upgrade. Sanitary Forcemain Replacement and Lift Station Upgrade.
Thorhild No. 7 (County), Alberta
Federal contribution
$2.1M
$2,071,550
Federal share33%
of $6.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
2016201720182019
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- County of Thorhild
- Construction start
- Jan 27, 2017(actual)
- Construction end
- Aug 2, 2019(actual)
Against the original forecast
- Construction start3 months earlyforecast May 1, 2017
- Construction end5 weeks lateforecast Jun 30, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46302 in the federal list. How to read these figures.