Water and Wastewater Line Replacement - Phase 1

Snow Lake, Manitoba

completeDrinking WaterSCF
Federal contribution
$611,793
Federal share33%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
20162017
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Snow Lake
Construction start
Jul 13, 2016(actual)
Construction end
Aug 28, 2017(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 27, 2016
  • Construction end10 months lateforecast Oct 31, 2016