Waterhen, Camperville & Duck Bay Water Treatment Plant Upgrades
Federal contribution
$198,128
Federal share33%
of $594.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
201620172018201920202021
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Manitoba Strategic Infrastructure Secretariat
- Construction start
- Jun 1, 2020(actual)
- Construction end
- Oct 29, 2020(actual)
Against the original forecast
- Construction start22 months lateforecast Jul 30, 2018
- Construction end3 months lateforecast Aug 7, 2020
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46322 in the federal list. How to read these figures.