Schedule

Announced and approvedJul 31, 2015
201620172018201920202021
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jun 1, 2020(actual)
Construction end
Oct 29, 2020(actual)

Against the original forecast

  • Construction start22 months lateforecast Jul 30, 2018
  • Construction end3 months lateforecast Aug 7, 2020