Sanford Wastewater Treatment Facility Expansion

MacDonald, Manitoba

completeWastewaterSCF
Federal contribution
$247,967
Federal share33%

of $743.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
20162017
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jun 27, 2016(actual)
Construction end
Jun 26, 2017(actual)

Against the original forecast

  • Construction end7 months lateforecast Nov 18, 2016