Birch River Water Treatment Plant Upgrades
Federal contribution
$166,666
Federal share33%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
201620172018201920202021
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Rural Municipality of Mountain
- Construction start
- Oct 13, 2020(actual)
- Construction end
- May 27, 2021(actual)
Against the original forecast
- Construction end5 months earlyforecast Oct 31, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46326 in the federal list. How to read these figures.