Onanole Water System Pump House and Reservoir

Harrison Park, Manitoba

completeDrinking WaterSCF
Federal contribution
$550,060
Federal share27%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
2016201720182019
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Aug 2, 2016(actual)
Construction end
Nov 14, 2018(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Nov 30, 2018