Back to projects

Chicot Lake Flood Control

St. Louis No. 431, Saskatchewan

completeDisaster MitigationSCF
Federal contribution
$400,000
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
201620182020202220242026
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Oct 17, 2016(actual)
Construction end
Aug 29, 2025(actual)

Against the original forecast

  • Construction end2.2 years earlyforecast Oct 31, 2027

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46355 in the federal list. How to read these figures.