Wastewater and Drinking Water Mains Infrastructure

Clavet, Saskatchewan

completeWastewaterSCF
Federal contribution
$470,876
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
20162017
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Clavet
Construction start
Jul 25, 2016(actual)
Construction end
Aug 10, 2017(actual)

Against the original forecast

  • Construction end6 weeks lateforecast Jun 30, 2017