Comprehensive Recycle Centre
Federal contribution
$383,343
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
201620172018
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Wynyard
- Construction start
- Apr 3, 2017(actual)
- Construction end
- Dec 7, 2017(actual)
Also in Wynyard
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46367 in the federal list. How to read these figures.