Back to projects

Water Treatment Plant Expansion and New Well

Waseca, Saskatchewan

completeDrinking WaterSCF
Federal contribution
$90,000
Federal share33%

of $270.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
2016201720182019
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Waseca
Construction start
Oct 20, 2017(actual)
Construction end
Mar 27, 2019(actual)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46375 in the federal list. How to read these figures.