Dundas Street West Rehabilitation - Coleman Street to Sidney Street
Federal contribution
$2.8M
$2,790,127
Federal share29%
of $9.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2015
20162017
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Belleville
- Construction start
- Sep 14, 2015(actual)
- Construction end
- Jul 21, 2017(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Sep 28, 2015
- Construction end2 months earlyforecast Oct 1, 2017
Also in Belleville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46386 in the federal list. How to read these figures.