Solar Energy Solution

Middlesex, Ontario

completeGreen EnergySCF
Federal contribution
$814,568
Federal share33%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2016
2016201820202022
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Oneida Nation of the Thames
Construction start
Sep 1, 2018(actual)
Construction end
Oct 29, 2021(actual)

Against the original forecast

  • Construction start3 months earlyforecast Dec 1, 2018
  • Construction end4 months lateforecast Jun 30, 2021