Kenojuak Cultural Centre Development

Cape Dorset, Nunavut

completeCultureSCF
Federal contribution
$2.0M
$2,000,000
Federal share47%

of $4.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 26, 2016
201720182019
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Hamlet of Cape Dorset
Construction start
May 1, 2017(actual)
Construction end
Feb 4, 2019(actual)

Against the original forecast

  • Construction end2.2 years earlyforecast Mar 31, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46412 in the federal list. How to read these figures.