Warman and Martensville Interchanges
Federal contribution
$30.0M
$30,000,000
Federal share48%
of $62.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 29, 2016
201720182019
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- City of Martensville
- Construction start
- Apr 1, 2017(actual)
- Construction end
- Jan 8, 2019(actual)
Against the original forecast
- Construction start4 weeks lateforecast Mar 1, 2017
- Construction end9 months earlyforecast Oct 1, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46417 in the federal list. How to read these figures.