Warman and Martensville Interchanges

Martensville, Saskatchewan

completeHighways and RoadsNRP
Federal contribution
$30.0M
$30,000,000
Federal share48%

of $62.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 29, 2016
201720182019
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
City of Martensville
Construction start
Apr 1, 2017(actual)
Construction end
Jan 8, 2019(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Mar 1, 2017
  • Construction end9 months earlyforecast Oct 1, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46417 in the federal list. How to read these figures.