Exshaw Creek Debris Flood Risk Mitigation

Bighorn No. 8, Alberta

completeDisaster MitigationNRP
Federal contribution
$2.0M
$1,988,135
Federal share33%

of $6.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 11, 2018
20192020
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Mar 27, 2019(actual)
Construction end
Jul 27, 2020(actual)

Against the original forecast

  • Construction end3 months earlyforecast Oct 30, 2020