Highway 43 Bundle

Greenview No. 16, Alberta

completeHighways and RoadsNRP
Federal contribution
$12.0M
$12,008,524
Federal share47%

of $25.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 20, 2017
20182019
Built
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
May 15, 2018(actual)
Construction end
Oct 30, 2019(actual)

Against the original forecast

  • Construction start12 months lateforecast May 1, 2017
  • Construction end2 months lateforecast Aug 15, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46493 in the federal list. How to read these figures.