Fundy Trail Connector Road
Federal contribution
$11.8M
$11,800,000
Federal share33%
of $35.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 2, 2016
2017201920212023
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of New Brunswick
- Construction start
- Mar 6, 2018(actual)
- Construction end
- Aug 17, 2023(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Apr 2, 2018
- Construction end2 months earlyforecast Oct 31, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46495 in the federal list. How to read these figures.