Highway 2 Bundle

Big Lakes, Alberta

completeHighways and RoadsNRP
Federal contribution
$18.3M
$18,308,500
Federal share50%

of $36.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 20, 2017
2018201920202021
Built
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Jul 15, 2017(actual)
Construction end
Oct 15, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2017

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46497 in the federal list. How to read these figures.