Wastewater Lagoon Expansion
Federal contribution
$204,728
Federal share33%
of $614.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 26, 2016
201720182019
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Drake
- Construction start
- Jul 11, 2016(actual)
- Construction end
- Jan 9, 2019(actual)
Against the original forecast
- Construction end3 months earlyforecast Mar 31, 2019