Back to projects

Water Treatment Plant Upgrade

Mankota, Saskatchewan

completeDrinking WaterSCF
Federal contribution
$283,333
Federal share33%

of $850.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 26, 2016
2016201720182019
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Mankota
Construction start
Sep 30, 2017(actual)
Construction end
Aug 29, 2019(actual)

Against the original forecast

  • Construction end17 months lateforecast Mar 31, 2018

Also in Mankota

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46540 in the federal list. How to read these figures.