Highway 16 Passing Lanes and Intersection Bundle
Federal contribution
$16.1M
$16,107,426
Federal share50%
of $32.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 25, 2016
2017201920212023
BuiltForecast
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of British Columbia
- Construction start
- May 22, 2017(actual)
- Construction end
- Jul 15, 2024(forecast)
Against the original forecast
- Construction start3 weeks lateforecast May 1, 2017
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46562 in the federal list. How to read these figures.