Carnduff Wastewater Treatment Lagoon

Carnduff, Saskatchewan

completeWastewaterNRP
Federal contribution
$2.9M
$2,854,166
Federal share32%

of $8.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 10, 2016
2017201920212023
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Town of Carnduff
Construction start
Aug 15, 2017(actual)
Construction end
Dec 21, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast May 15, 2017
  • Construction end7 weeks lateforecast Nov 1, 2023