Nipawin Water Treatment Plant
Federal contribution
$6.4M
$6,413,412
Federal share33%
of $19.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 13, 2016
2017201920212023
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Town of Nipawin
- Construction start
- May 12, 2016(actual)
- Construction end
- Dec 14, 2023(actual)
Against the original forecast
- Construction start3 months earlyforecast Jul 31, 2016
- Construction end8 months lateforecast Mar 31, 2023
Also in Nipawin