Back to projects

Wastewater Treatment System Upgrades

Pilot Butte, Saskatchewan

completeWastewaterNRP
Federal contribution
$2.2M
$2,166,666
Federal share20%

of $10.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2017
2018201920202021
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Town of Pilot Butte
Construction start
Sep 3, 2019(actual)
Construction end
Aug 17, 2021(actual)

Against the original forecast

  • Construction start5 months lateforecast Mar 31, 2019
  • Construction end2 weeks lateforecast Jul 31, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46580 in the federal list. How to read these figures.