Wastewater Treatment System Upgrades
Federal contribution
$2.2M
$2,166,666
Federal share20%
of $10.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 17, 2017
2018201920202021
Built
Approved 2 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Town of Pilot Butte
- Construction start
- Sep 3, 2019(actual)
- Construction end
- Aug 17, 2021(actual)
Against the original forecast
- Construction start5 months lateforecast Mar 31, 2019
- Construction end2 weeks lateforecast Jul 31, 2021