Rehabilitation of the Billy-Diamond Road (formerly known as the James Bay Road)
Federal contribution
$108.3M
$108,337,779
Federal share49%
of $222.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 10, 2017
20182019202020212022
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Société de développement de la Baie-James
- Construction start
- Jul 11, 2017(actual)
- Construction end
- Oct 1, 2022(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Oct 31, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46586 in the federal list. How to read these figures.