Rehabilitation of the Billy-Diamond Road (formerly known as the James Bay Road)

Baie-James, Quebec

completeHighways and RoadsNRP
Federal contribution
$108.3M
$108,337,779
Federal share49%

of $222.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 10, 2017
20182019202020212022
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Jul 11, 2017(actual)
Construction end
Oct 1, 2022(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Oct 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46586 in the federal list. How to read these figures.