Route 11 (Shediac to Miramichi) Upgrades
Federal contribution
$42.4M
$42,400,000
Federal share50%
of $84.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 13, 2017
2017201920212023
Built
Approved 8 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of New Brunswick
- Construction start
- Mar 20, 2017(actual)
- Construction end
- Jan 15, 2024(actual)
Against the original forecast
- Construction end3 months lateforecast Oct 30, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46589 in the federal list. How to read these figures.