Rehabilitation on the Trans Canada Highway (between routes 340 and 360)
Lewisporte, Newfoundland and Labrador
Federal contribution
$596,989
Federal share44%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 18, 2016
Built
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Government of Newfoundland and Labrador
- Construction start
- Jul 7, 2016(actual)
- Construction end
- Sep 30, 2016(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 6, 2016
- Construction end4 weeks earlyforecast Oct 31, 2016
Also in Lewisporte
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46595 in the federal list. How to read these figures.