Paulatuk, Gameti, Wekweeti Water Treatment Bundle
Federal contribution
$1.5M
$1,500,000
Federal share16%
of $9.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2016
201620172018201920202021
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Government of Northwest Territories
- Construction start
- Jun 1, 2018(actual)
- Construction end
- Mar 31, 2021(actual)
Against the original forecast
- Construction end8 months earlyforecast Dec 1, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46613 in the federal list. How to read these figures.