Back to projects

Chlorination Building Upgrades

Birchy Bay, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$131,257
Federal share33%

of $393.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 20, 2016
2017
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Birchy Bay
Construction start
Jun 12, 2017(actual)
Construction end
Nov 28, 2017(actual)

Against the original forecast

  • Construction start13 months lateforecast May 15, 2016
  • Construction end4 weeks lateforecast Oct 31, 2017

Also in Birchy Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46662 in the federal list. How to read these figures.