Conception Bay Highway Water Main Upgrades, Main Beach Lift Station Upgrades, Pressure Reducing Valves, and Filtration System
Holyrood, Newfoundland and Labrador
Federal contribution
$350,442
Federal share31%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 20, 2016
2017201920212023
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Holyrood
- Construction start
- Sep 28, 2016(actual)
- Construction end
- Feb 1, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast May 15, 2016
- Construction end5 weeks lateforecast Dec 31, 2022