Back to projects

Conception Bay Highway Water Main Upgrades, Main Beach Lift Station Upgrades, Pressure Reducing Valves, and Filtration System

Holyrood, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$350,442
Federal share31%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 20, 2016
2017201920212023
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Holyrood
Construction start
Sep 28, 2016(actual)
Construction end
Feb 1, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast May 15, 2016
  • Construction end5 weeks lateforecast Dec 31, 2022

Also in Holyrood