Water Treatment Plant Upgrades
Musgrave Harbour, Newfoundland and Labrador
Federal contribution
$163,392
Federal share33%
of $490.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 20, 2016
201720182019
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Musgrade Harbour
- Construction start
- Aug 10, 2016(actual)
- Construction end
- Mar 21, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast May 15, 2016
- Construction end3 months earlyforecast Jun 30, 2019
Also in Musgrave Harbour
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46674 in the federal list. How to read these figures.