Back to projects

Water Treatment Plant Upgrades

Musgrave Harbour, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$163,392
Federal share33%

of $490.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 20, 2016
201720182019
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Musgrade Harbour
Construction start
Aug 10, 2016(actual)
Construction end
Mar 21, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast May 15, 2016
  • Construction end3 months earlyforecast Jun 30, 2019