Back to projects

Alternate Water Supply

Steady Brook, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$145,391
Federal share25%

of $586.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 20, 2016
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Steady Brook
Construction start
Aug 16, 2016(actual)
Construction end
Nov 19, 2016(actual)

Against the original forecast

  • Construction start3 months lateforecast May 15, 2016
  • Construction end11 months earlyforecast Oct 31, 2017

Also in Steady Brook