New Water Storage Tank
Indian Bay, Newfoundland and Labrador
Federal contribution
$133,067
Federal share32%
of $420.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 20, 2016
201720182019
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Indian Bay
- Construction start
- Apr 15, 2018(actual)
- Construction end
- Jun 24, 2019(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Jun 1, 2018
- Construction end5 months earlyforecast Nov 30, 2019