Replacement of wastewater/potable water pipes in the village of La Guadeloupe

La Guadeloupe, Quebec

completeWastewaterSCF
Federal contribution
$110,756
Federal share33%

of $332.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2017201920212023
Built

Approved 11 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of La Guadeloupe
Construction start
May 1, 2016(actual)
Construction end
Aug 22, 2023(actual)

Against the original forecast

  • Construction end6.4 years lateforecast Mar 31, 2017

Also in La Guadeloupe

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46693 in the federal list. How to read these figures.