Northern Drinking Water Supply, Treatment, and Reservoir Upgrades

Beauval, Saskatchewan

completeDrinking WaterNRP
Federal contribution
$5.0M
$5,040,904
Federal share33%

of $15.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 13, 2016
2017201920212023
Built

Approved 3 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Apr 15, 2017(actual)
Construction end
Mar 31, 2023(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast May 19, 2017
  • Construction end5 months lateforecast Oct 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46696 in the federal list. How to read these figures.