2016 Bridge and Collector Roads Bundle

Alberton, Prince Edward Island

completeHighways and RoadsNRP
Federal contribution
$1.9M
$1,870,503
Federal share48%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2016
2017
Built
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Jul 16, 2016(actual)
Construction end
Nov 24, 2017(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 6, 2016
  • Construction end4 months lateforecast Jul 30, 2017

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46714 in the federal list. How to read these figures.