Petitcodiac River Restoration Project Bridge and Channel Construction
Federal contribution
$21.0M
$21,011,520
Federal share39%
of $54.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 16, 2016
20172019202120232025
Built
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of New Brunswick
- Construction start
- May 31, 2017(actual)
- Construction end
- Oct 22, 2024(actual)
Against the original forecast
- Construction start6 weeks lateforecast Apr 17, 2017
- Construction end17 months lateforecast Jun 1, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46718 in the federal list. How to read these figures.