Highway 102/103: Interchange Upgrade and Structure Replacement
Federal contribution
$9.4M
$9,405,000
Federal share50%
of $18.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2017
201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of Nova Scotia
- Construction start
- Mar 12, 2018(actual)
- Construction end
- Jan 7, 2020(actual)
Against the original forecast
- Construction start6 months lateforecast Sep 1, 2017
Also in Halifax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46731 in the federal list. How to read these figures.