Back to projects

Paving Pond Road

Lord's Cove, Newfoundland and Labrador

completeHighways and RoadsSCF
Federal contribution
$105,624
Federal share29%

of $360.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
2017
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Lord's Cove
Construction start
Jun 12, 2017(actual)
Construction end
Sep 30, 2017(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 17, 2017

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46746 in the federal list. How to read these figures.