Highway 11/17 Expansion - Coughlin Road Westerly to Highway 582 (including Valley Creek Culverts)

Lyon, Ontario

underwayHighways and RoadsMIC
Federal contribution
$27.0M
$26,972,980
Federal share50%

of $53.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 15, 2017
20172019202120232025
BuiltForecast

Approved 9 months before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Sep 1, 2022(actual)
Construction end
Jun 30, 2026(forecast)

Against the original forecast

  • Construction start2.6 years lateforecast Feb 1, 2020

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46767 in the federal list. How to read these figures.