Back to projects

Water Treatment Plant Upgrade

Cape Croker, Ontario

completeDrinking WaterSCF
Federal contribution
$500,000
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 7, 2016
20172019202120232025
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Sep 3, 2018(actual)
Construction end
Jul 31, 2025(actual)

Against the original forecast

  • Construction start20 months lateforecast Jan 2, 2017
  • Construction end7 months lateforecast Dec 31, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46837 in the federal list. How to read these figures.